NOTE

:
Before removing and installing any control units, first turn the ignition switch to the LOCK position, then disconnect both battery cables.

After finishing work, confirm that all control unit connectors are connected properly, then re-connect both battery cables.

Always use CONSULT-III to perform self-diagnosis as a part of each function inspection after finishing work.

If a DTC is detected, perform trouble diagnosis according to self-diagnosis results.

For vehicle with steering lock unit, if the battery is disconnected or discharged, the steering wheel will lock and cannot be turned.

If turning the steering wheel is required with the battery disconnected or discharged, follow the operation procedure below before starting the repair operation.

OPERATION PROCEDURE

1. Connect both battery cables.

NOTE

:
Supply power using jumper cables if battery is discharged.

2. Turn the ignition switch to ACC position. (At this time, the steering lock will be released.)
3. Disconnect both battery cables. The steering lock will remain released with both battery cables disconnected and the steering wheel can be turned.

4. Perform the necessary repair operation.

5. When the repair work is completed, re-connect both battery cables. With the brake pedal released, turn the ignition switch from ACC position to ON position, then to LOCK position. (The steering wheel will lock when the ignition switch is turned to LOCK position.) 6. Perform self-diagnosis check of all control units using CONSULT-III.

    Precaution for Supplemental Restraint System (SRS) "AIR BAG" and "SEAT BELT PRE-TENSIONER"
    The Supplemental Restraint System such as AIR BAG and SEAT BELT PRE-TENSIONER, used along with a front seat belt, helps to reduce the risk or severity of injury to the driver and front passen ...

    Precaution for Procedure without Cowl Top Cover
    When performing the procedure after removing cowl top cover, cover the lower end of windshield with urethane, etc. ...

    Other materials:

    Oil pressure switch signal circuit
    Component Function Check 1.CHECK COMBINATION METER INPUT SIGNAL Select the Data Monitor for the METER/M&A and check the OIL W/L monitor value. OIL W/L Ignition switch ON : On Engine running : Off >> INSPECTION END Diagnosis Procedure 1.CHECK OIL PRESSURE SWITCH CIRCUIT 1 ...

    Combination switch output circuit
    Diagnosis Procedure 1.CHECK OUTPUT 1 - 5 CIRCUIT FOR OPEN 1. Turn ignition switch OFF. 2. Disconnect BCM and combination switch connectors. 3. Check continuity between BCM harness connector and combination switch harness connector. Does continuity exist? YES >> GO TO 2. NO >> ...

    Inspection
    INSPECTION AFTER INSTALLATION Check accelerator pedal moves smoothly within the whole operation range when it is fully depressed and released. Check accelerator pedal securely returns to the fully released position. For the electrical inspection of accelerator pedal position sensor. Refe ...