Nissan Juke Service and Repair Manual : Precaution Necessary for Steering Wheel Rotation after Battery Disconnect

NOTE

:
Before removing and installing any control units, first turn the push-button ignition switch to the LOCK position, then disconnect both battery cables.

After finishing work, confirm that all control unit connectors are connected properly, then re-connect both battery cables.

Always use CONSULT-III to perform self-diagnosis as a part of each function inspection after finishing work.

If a DTC is detected, perform trouble diagnosis according to self-diagnosis results.

For vehicle with steering lock unit, if the battery is disconnected or discharged, the steering wheel will lock and cannot be turned.

If turning the steering wheel is required with the battery disconnected or discharged, follow the operation procedure below before starting the repair operation.

OPERATION PROCEDURE

1. Connect both battery cables.

NOTE

:
Supply power using jumper cables if battery is discharged.

2. Turn the push-button ignition switch to ACC position.

(At this time, the steering lock will be released.) 3. Disconnect both battery cables. The steering lock will remain released with both battery cables disconnected and the steering wheel can be turned.

4. Perform the necessary repair operation.

5. When the repair work is completed, re-connect both battery cables. With the brake pedal released, turn the push-button ignition switch from ACC position to ON position, then to LOCK position. (The steering wheel will lock when the push-button ignition switch is turned to LOCK position.)
6. Perform self-diagnosis check of all control units using CONSULT-III.

    Precaution for Procedure without Cowl Top Cover
    When performing the procedure after removing cowl top cover, cover the lower end of windshield with urethane, etc. ...

    Precaution for Supplemental Restraint System (SRS) "AIR BAG" and "SEAT BELT PRE-TENSIONER"
    The Supplemental Restraint System such as AIR BAG and SEAT BELT PRE-TENSIONER, used along with a front seat belt, helps to reduce the risk or severity of injury to the driver and front passen ...

    Other materials:

    Main line betweeN DLC and MDU circuit
    Diagnosis Procedure 1.CHECK HARNESS CONTINUITY (OPEN CIRCUIT) 1. Turn the ignition switch OFF. 2. Disconnect the battery cable from the negative terminal. 3. Disconnect the following harness connectors. - ECM - Multi display unit 4. Check the continuity between the data link connector and the ...

    Push starting
    Do not attempt to start the engine by pushing. CAUTION Continuously Variable Transmission (CVT) models cannot be pushstarted or tow-started. Attempting to do so may cause transmission damage. Three-way catalyst equipped models should not be started by pushing since the three way catalyst ...

    Service
    Never use electrical test equipment to check SRS circuits unless instructed to in this Service Manual. Before servicing the SRS, turn ignition switch OFF, disconnect battery negative terminal and wait at least 3 minutes. For approximately 3 minutes after the battery negative terminal ar ...